CONSTRUCTION UPDATES

KEEP UP TO DATE WITH THE LATEST CONSTRUCTION UPDATES ON ELAN

1st August 2017

• Level 5 concrete slab formwork in progress for one tower
• Level 4 concrete pour completed Saturday, 29 July 2017
• Basement formwork stripping commenced in July 2017
• Commenced framing walls on Level 1 at the end of July 2017

image

15th June 2017

• Street level deck (second level) with reinforcement installation is currently in progress
• Services installation to basement to commence soon
• Elan is still on track for completion around the 3r quarter of 2018

image
divider

EXQUISITE 1, 2 & 3 BEDROOM APARTMENTS

REGISTER YOUR INTEREST BELOW

Onsite Display Apartment now open for inspection by appointment

DISCLAIMER:

Please note the material contained herein has been produced prior to detailed design and construction, is indicative only and does not constitute a representation by the Vendor, Agent or Vendor’s consultant in respect to the size, form, dimensions, specifications or layout of the apartment or at all. The final product may change from that illustrated herein. Furniture is not included. All furniture shown is for illustration purposes only. Changes may be made to the detail layouts during the development in accordance with the provisions of the contract of sale or the building and or planning requirements or for compliance with relevant standards or codes. Prospective purchasers must make and rely on their own enquiries.

Design by rareid.com.au